2020-04 Lonesome Dove Trail Drainage Culvert Extension

Overall Percent Complete

10%

2020-04Timeline

Status: Project completed submission of 90% design package, with bid issuance scheduled for August 2020.

50.90 D-1      Reinforced Concrete Box Culvert Extension:

Installation of drainage pipe to fill in the area of bar ditches to Maxwell Creek providing for the reduction of perpetual maintenance and more access to open space for the community.

50.91 D-2      Reinforced Concrete Pipe Culvert:

Installation of drainage pipe to fill in the area of bar ditches to Maxwell Creek providing for the reduction of perpetual maintenance and more access to open space for the community.

50.92 D-3       Reinforced Concrete Pipe Culverts:

Installation of drainage pipe to fill in the area of bar ditches to Maxwell Creek providing for the reduction of perpetual maintenance and more access to open space for the community.

50.92 D-4      Reinforced Concrete Pipe Culverts:

Installation of drainage pipe to fill in the area of bar ditches to Maxwell Creek providing for the reduction of perpetual maintenance and more access to open space for the community.

Area Impacted:

Lonesome Dove Trail